Gargai Dam Gets NBWL Wildlife Clearance; BMC Eyes Early 2027 Construction Start
Mumbai's civic body still needs forest, land and rehabilitation approvals before work begins on the 440 MLD project in Palghar.

The Standing Committee of the National Board for Wildlife (NBWL) has cleared the Gargai Dam project, a 440 million litres per day (MLD) addition to Mumbai's water supply. The meeting was chaired by the Union Environment Minister in Delhi on Monday, according to the report. The Brihanmumbai Municipal Corporation (BMC) is still waiting for the official minutes.
The BMC says wildlife clearance is only one step. It needs two more forest clearances, one from the Maharashtra government and one from the Centre. Land requirements, compensatory afforestation, and approvals for the rehabilitation and resettlement of affected villages are also pending. A senior civic official said the BMC expects these within two months, which would allow construction to start in early 2027.
The corporation has already started moving machinery and manpower to the site. It wants to finish the dam and related structures by May-June 2029 and begin storing and supplying water by the 2029 monsoon.
The timeline is tight. The BMC plans to build the main dam in nine months. The Middle Vaitarna dam took 15 months and has been ranked the ninth-fastest dam build in the world. The Central Design Organisation in Nashik, the state's apex technical body for dams, has cleared the basic design and structural aspects. The dam will use roller-compacted concrete.
The project is in Wada taluka of Palghar district. It involves a 69-metre-high dam near Ogada village and a 2.2-km tunnel to divert water into the Modak Sagar reservoir.
The environmental cost is significant. About 3.1 lakh trees will have to be felled, including in areas inside the Tansa Wildlife Sanctuary. Compensatory afforestation must be done on non-forest land.
The BMC supplies roughly 4,100 MLD from seven lakes: Tansa, Bhatsa, Modak Sagar, Tulsi, Vihar, Upper Vaitarna and Middle Vaitarna. Around 34 per cent of that is reportedly lost to leakages and theft. Demand is estimated at 4,463 MLD and is projected to reach 6,900 MLD by 2041. Gargai would be the first major addition since Middle Vaitarna was completed in 2014, if the remaining approvals and rehabilitation work stay on schedule.